- Question #1PRINCE2 Principles
Which of the following principles describes this statement?" xxx defines tolerances for each project objective to establish limits of delegated authority"
manage by exceptiontolerancesdelegated authorityPRINCE2 principles - Question #2PRINCE2 Principles
Which of the following statements is NOT correct? The Learn from Experience principle suggests that lessons should be actively sought...
learn from experienceproject initiationlessonsPRINCE2 principles - Question #3PRINCE2 Principles
Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality met...
focus on productsproduct descriptionsquality criteriaPRINCE2 principles - Question #4PRINCE2 Principles
Which of the following statements is FALSE regarding the Continued Business Justification?
continued business justificationbusiness caseproject viabilityPRINCE2 principles - Question #5PRINCE2 Principles
The Manage by Exception principle sets tolerances for six areas of the project, Time. Cost and Quality are three of them, what are the other three?
manage by exceptiontolerancesscope risk benefitPRINCE2 principles - Question #7Business Case Theme
Which of the following statements describes an outcome?
outcomesoutputsbenefitsPRINCE2 terminology - Question #8Business Case Theme
Which of the following should NOT be included in the business case?
business casebusiness approachproject justificationPRINCE2 documents - Question #9Business Case Theme
When considering the business options in the business case, which of these is NOT an option?
business optionsdo nothingdo minimumbusiness case - Question #10Business Case
Which of the following statements is TRUE with regard to expected benefits?
expected benefitsBusiness Casemeasurabilitybenefit tolerances - Question #11Organization
Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
Business Assurancevalue for moneyproject assurance rolesOrganization - Question #13Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
Business Case causesproject justificationscenario analysisreasons for project - Question #14Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
Business Case optionsdo nothing optionscenario analysisproject scope - Question #15Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
expected benefitsbenefit measurementBusiness Casescenario analysis - Question #16Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
dis-benefitsBusiness Case risksscenario analysisnegative outcomes - Question #17Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
Business Case timescalesbenefit tolerancesconstraintsscenario analysis - Question #18Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
Business Case costsfunding sourcecost estimationscenario analysis - Question #19Business Case
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar...
Business Case risksbenefit realizationscenario analysisrisk identification - Question #21Business Case
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
Business Case reasonsproject justificationscenario analysisMFH outsourcing - Question #22Business Case
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
Business Case optionsoutsourcingscenario analysisoption appraisal - Question #23Business Case
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
expected benefitscost savingsBusiness Casescenario analysis - Question #24
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
- Question #25Business Case
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
benefit realization timingBusiness Case timescalesstage planningscenario analysis - Question #26Business Case
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion...
Business Case risksoutsourcing risksscenario analysisproject threats - Question #28Organization
Which of the following is False?
Project Boardteam managementgovernanceOrganization - Question #29Organization
Which of the following statements is true of the business interest on the project?
Executive rolebusiness interestvalue for moneyOrganization - Question #30Organization
Which of the following represents the four key characteristics a good Project board should display?
Project Board characteristicsauthoritycredibilityOrganization - Question #31Change
In which Management product would the Project Board specify where the authority for change requests lies?
Configuration Management Strategychange authorityChange themechange control - Question #32Organization
Who is responsible for ensuring that Communication Management Strategy is appropriate and that planned communication activities actually take place?
Communication Management StrategyProject Assurancestakeholder communicationOrganization - Question #33Organization Theme
Which of the following roles cannot be combined?
Project Board rolesrole combinationsSenior UserExecutive - Question #35Organization Theme
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his vis...
Executive roleProject Boardauthoritystrategic oversight - Question #36Organization Theme
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his vis...
Senior User roleuser representationbenefits realizationProject Board - Question #37Organization Theme
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his vis...
Senior User rolestakeholder interestsuser representationProject Board - Question #38Organization Theme
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his vis...
Senior User responsibilitiesstakeholder engagementconflict resolutionProject Board - Question #40Organization Theme
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his vis...
Project Supportconfiguration managementquality assuranceorganizational standards - Question #42Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Executive roleProject BoardSenior Supplierrole assignment - Question #43Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Senior Supplier roleProject Boardsupplier authorityuser representation - Question #44Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Senior User roleProject Board compositionuser representationdivision representation - Question #45Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Project AssuranceBusiness AssuranceProject Boardfinance oversight - Question #46Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Project AssuranceSupplier Assuranceindependenceproduct integrity - Question #47Organization Theme
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that...
Senior User roleProject Boardstakeholder communicationuser perspective - Question #49Quality Theme
Which principle is central to the quality theme and provides explicit understanding of what the project will create?
Focus on Products principlequality themePRINCE2 principlesproduct-based planning - Question #50Quality Theme
Which of the following statements are True: 1. Quality management is the complete set of quality standards, procedures and responsibilities for a site or organization. 2. Quality p...
quality managementquality planningquality controlquality assurance - Question #51
Which of the following statements would NOT be included in the Project Product Description?
- Question #52Quality Theme
In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator:
quality review techniqueadministrator roleProject Supportquality inspection - Question #53Quality Theme
Which role is responsible for providing the customer's quality expectations and acceptance criteria for the project?
Senior User responsibilitiesquality expectationsacceptance criteriacustomer quality - Question #54Quality Theme
Which management product defines the detailed nature, purpose and function of a product?
Product Descriptionmanagement productsproduct definitionquality criteria - Question #57Quality Theme
Extract from the Project Product Description (with errors)
Project Product Descriptioncompositionscopeproduct errors - Question #58Quality Theme
Extract from the Project Product Description (with errors) Which 2 statements apply to the Derivation section?
Project Product Descriptionderivationdevelopment skillsproduct description sections - Question #59Quality Theme
Extract from the Project Product Description (with errors) Which 2 statements apply to the Development skills required section?
Project Product Descriptiondevelopment skillscompositionderivation - Question #60Quality
Extract from the Project Product Description (with errors) Which 2 statements apply to the Customer's quality expectations section?
Project Product Descriptioncustomer quality expectationsquality themeproduct management