PRINCE2-FOUNDATION Exam Questions
1,059 real PRINCE2-FOUNDATION exam questions with expert-verified answers and explanations. Page 8 of 22.
- Question #355
A pre-requisite of effective issue and change control is the establishment of which of the following?
- Question #356
Which of the following are typical activities of a configuration management procedure? 1. Impact assessment 2. Control 3. Verification and audit 4. Status accounting
- Question #357
Which statement is FALSE regarding a Product Status Account?
- Question #358
Which product is continuously maintained in order to inform the Project Manager of where a product is at any time, what its status is and who is working on it?
- Question #359
Identify the missing word(s) in the following sentence... Change can only be considered in relation to an established [ ? ]
- Question #360
Can a baselined management product be changed once it has been approved?
- Question #361
According to PRINCE2, what are issues likely to affect?
- Question #362
Which of the following tasks is the first to be performed on receipt of a new issue?
- Question #363
Which of the following is a concession?
- Question #364
A stakeholder wishing to make an observation about the project would do what?
- Question #365
Which product identifies how changes to products will be controlled and where the products will be stored?
- Question #366
Which product is used to record and maintain information regarding any issues that are being managed formally?
- Question #367
According to PRINCE2, Which of the following would be used to pay for a request for change and possibly any analysis costs?
- Question #368
Which of the following are tasks carried out as part of product-based planning? 1. Write a Project Product Description. 2. Identify activities and dependencies 3. Create a product...
- Question #369
Where would a Team Manager find information regarding the specific quality required for a product?
- Question #370
Which of the following is NOT a purpose of a Product Description?
- Question #371
What is NOT identified when creating a product breakdown structure?
- Question #372
Which plan is optional depending on the complexity of the project?
- Question #373
Identify the missing word(s) in the following sentence... PRINCE2 recommends three [ ? ] to reflect the needs of the different levels of management involved in a project.
- Question #374
Which of the following is NOT one of the three levels of plan recommended by PRINCE2?
- Question #375
The period of time for which it is possible to accurately plan in detail is known as?
- Question #376
Which of the following shows the scope of a plan?
- Question #377
Which product does the Project Board use as a base against which to monitor project progress on a stage by stage basis?
- Question #378
According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?
- Question #379
Why does PRINCE2 recommend having three levels of plan?
- Question #380
Which of the following Plans can be approved by the Project Manager?
- Question #381
In which process is it decided that an Exception Plan should be created to replace a Stage Plan?
- Question #382
Which product identifies the source products from which a product is to be derived?
- Question #383
Which PRINCE2 theme has a purpose to facilitate communication and control by defining the means of delivering the products?
- Question #384
Identify the missing word(s) in the following sentence... The development and maintenance of a credible [?] provides a baseline against which progress can be measured.
- Question #385
Which of the following would define the sequence in which the products are to be created and any dependencies between them?
- Question #386
According to PRINCE2, Project Board members would NOT be involved in which of the following?
- Question #387
Which product is the Executive specifically responsible for overseeing the development of?
- Question #388
Which of the following does PRINCE2 say are typical characteristics of a Project Board member?
- Question #389
Who is responsible for providing the project mandate?
- Question #390
Who determines the use of a change authority and change budget during project initiation?
- Question #391
Which role is the key decision-maker on the project management team and is ultimately accountable for the project's success?
- Question #392
If the Project Board wish to ensure the Communications Management Strategy covers all the stakeholders requirements for the next stage, which project management team role may they...
- Question #393
Which is a purpose of the Organization theme?
- Question #394
According to PRINCE2, which of the following roles can the Project Manager also undertake?
- Question #395
What is a purpose of the Communication Management Strategy?
- Question #396
What is a responsibility of the business representative on the Project Board?
- Question #397
Which is a responsibility of the Project Manager?
- Question #398
Which of the following roles can the Project Manager also perform? 1. Change Authority 2. Project Assurance 3. Project Support 4. Team Manager
- Question #399
What is defined within the Organization theme?
- Question #400
PRINCE2 defines which of the following three primary stakeholder categories?
- Question #401
User and Supplier are two of the three primary stakeholder interests that must be represented on the Project Board at all times. What is the third interest?
- Question #402
Which of the following management levels sits outside the project management team, but will be responsible for commissioning a project?
- Question #403
Which role organizes and chairs any Project Board reviews?
- Question #404
Which role is responsible for ensuring that the expected benefits are realized?