PRINCE2-FOUNDATION · Question #381

In which process is it decided that an Exception Plan should be created to replace a Stage Plan?

The correct answer is A. Directing a Project. See the full explanation below for the reasoning.

Question

In which process is it decided that an Exception Plan should be created to replace a Stage Plan?

Options

  • ADirecting a Project
  • BControlling a Stage
  • CManaging a Stage Boundary
  • DClosing a Project

How the community answered

(36 responses)
  • A
    83% (30)
  • B
    3% (1)
  • C
    6% (2)
  • D
    8% (3)