PRINCE2-FOUNDATION · Question #355

A pre-requisite of effective issue and change control is the establishment of which of the following?

The correct answer is C. A configuration management system. See the full explanation below for the reasoning.

Question

A pre-requisite of effective issue and change control is the establishment of which of the following?

Options

  • AUse of a change budget and change authority
  • BA risk management procedure
  • CA configuration management system
  • DA Quality Management Strategy

How the community answered

(24 responses)
  • A
    13% (3)
  • B
    4% (1)
  • C
    75% (18)
  • D
    8% (2)