The correct answer is C. A configuration management system. See the full explanation below for the reasoning.
Question
A pre-requisite of effective issue and change control is the establishment of which of the following?
Options
- AUse of a change budget and change authority
- BA risk management procedure
- CA configuration management system
- DA Quality Management Strategy