nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #355

PRINCE2-FOUNDATION Question #355: Real Exam Question with Answer & Explanation

The correct answer is C. A configuration management system. See the full explanation below for the reasoning.

Question

A pre-requisite of effective issue and change control is the establishment of which of the following?

Options

  • AUse of a change budget and change authority
  • BA risk management procedure
  • CA configuration management system
  • DA Quality Management Strategy

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice