Which of the following shows the scope of a plan?

The correct answer is B. The related product breakdown structure. See the full explanation below for the reasoning.

Question

Which of the following shows the scope of a plan?

Options

  • AThe full content of a product checklist
  • BThe related product breakdown structure
  • CThe composition of a Project Product Description
  • DAll of the project's Configuration Item Records

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    83% (24)
  • C
    10% (3)
  • D
    3% (1)