Which of the following is a concession?
The correct answer is C. When an off-specification is accepted by the Project Board or Change Authority without. See the full explanation below for the reasoning.
Question
Which of the following is a concession?
Options
- AWhen a product fails to meet its quality criteria
- BWhen an off-specification is raised by the Senior User
- CWhen an off-specification is accepted by the Project Board or Change Authority without
- DWhen a known error is no longer a problem
How the community answered
(21 responses)- A14% (3)
- B5% (1)
- C71% (15)
- D10% (2)
Community Discussion