PeopleCert
PRINCE2-FOUNDATION · Question #364
A stakeholder wishing to make an observation about the project would do what?
The correct answer is B. Raise an issue. See the full explanation below for the reasoning.
Question
A stakeholder wishing to make an observation about the project would do what?
Options
- AAsk for it to be included in the Communication Management Strategy
- BRaise an issue
- CMake an entry in the Issue Register
- DArrange a meeting with a Project Board member
How the community answered
(22 responses)- A9% (2)
- B68% (15)
- C5% (1)
- D18% (4)
Community Discussion
No community discussion yet for this question.