According to PRINCE2, Which of the following would be used to pay for a request for change and possibly any analysis costs?

The correct answer is C. Change budget. See the full explanation below for the reasoning.

Question

According to PRINCE2, Which of the following would be used to pay for a request for change and possibly any analysis costs?

Options

  • AContingency
  • BTolerance
  • CChange budget
  • DRisk budget

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    9% (3)
  • C
    82% (27)
  • D
    3% (1)