According to PRINCE2, Project Board members would NOT be involved in which of the following?
The correct answer is C. Running of the project on a day-to-day basis. See the full explanation below for the reasoning.
Question
According to PRINCE2, Project Board members would NOT be involved in which of the following?
Options
- AConfirming project tolerances with corporate or programme management
- BAuthorizing the start of the project
- CRunning of the project on a day-to-day basis
- DCommunications between the project management team and stakeholders external to that
How the community answered
(33 responses)- A9% (3)
- B6% (2)
- C82% (27)
- D3% (1)