The correct answer is B. Ensuring the project represents value for money. See the full explanation below for the reasoning.

Question

What is a responsibility of the business representative on the Project Board?

Options

  • ASetting tolerance levels for the project
  • BEnsuring the project represents value for money
  • CConfirming the project delivers the required functionality
  • DChecking the required quality levels are achieved by the project's products