The correct answer is B. Ensuring the project represents value for money. See the full explanation below for the reasoning.
Question
What is a responsibility of the business representative on the Project Board?
Options
- ASetting tolerance levels for the project
- BEnsuring the project represents value for money
- CConfirming the project delivers the required functionality
- DChecking the required quality levels are achieved by the project's products