PRINCE2-FOUNDATION · Question #360

PRINCE2-FOUNDATION Question #360: Real Exam Question with Answer & Explanation

The correct answer is D. Yes, as long as it is agreed with the relevant authority before it takes place. See the full explanation below for the reasoning.

Question

Can a baselined management product be changed once it has been approved?

Options

  • ANo, change control is there to prevent changes
  • BYes, there is no restriction
  • CYes, but only if the users say so
  • DYes, as long as it is agreed with the relevant authority before it takes place