nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #360

Can a baselined management product be changed once it has been approved?

The correct answer is D. Yes, as long as it is agreed with the relevant authority before it takes place. See the full explanation below for the reasoning.

Question

Can a baselined management product be changed once it has been approved?

Options

  • ANo, change control is there to prevent changes
  • BYes, there is no restriction
  • CYes, but only if the users say so
  • DYes, as long as it is agreed with the relevant authority before it takes place

How the community answered

(19 responses)
  • A
    11% (2)
  • C
    5% (1)
  • D
    84% (16)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice