ITSM20F.EN · Question #143

Targets for resolution should be based on priority. When scheduling Incident or Problem resolution, which of the following should not be taken into account?

The correct answer is D. the number of previously reported Incidents for the particular Configuration Item (CI). You've hit your weekly limit · resets 5am (America/New_York)

Resolution processes

Question

Targets for resolution should be based on priority. When scheduling Incident or Problem resolution, which of the following should not be taken into account?

Options

  • Athe available skills
  • Bthe competing requirements for resources
  • Cthe effort/cost to provide the method of resolution
  • Dthe number of previously reported Incidents for the particular Configuration Item (CI)

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    16% (6)
  • C
    8% (3)
  • D
    73% (27)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#incident resolution#problem scheduling#priority#resource management