ISEB-PM1 · Question #606

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

The correct answer is D. All of the other alternatives apply. You've hit your weekly limit · resets 5am (America/New_York)

The Project Management Lifecycle

Question

Lessons learned are most often based upon project historical records. Lessons learned can be used to:

Options

  • ASee how others have solved problems
  • B"Predict trends, highlight problems and identify alternatives"
  • CSee what mistakes others have made
  • DAll of the other alternatives apply

How the community answered

(36 responses)
  • A
    14% (5)
  • B
    3% (1)
  • C
    8% (3)
  • D
    75% (27)

Explanation