ISEB-PM1 · Question #607

In which type of organization(s) is the project manager's role most likely part-time?

The correct answer is D. Both 1) Functional and 2) Weak Matrix. You've hit your weekly limit · resets 5am (America/New_York)

Organizational Aspects of Project Management

Question

In which type of organization(s) is the project manager's role most likely part-time?

Options

  • AFunctional
  • BWeak Matrix
  • CBalanced Matrix
  • DBoth 1) Functional and 2) Weak Matrix

How the community answered

(19 responses)
  • A
    21% (4)
  • B
    5% (1)
  • C
    5% (1)
  • D
    68% (13)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#organizational structure#functional organization#weak matrix#project manager authority

Community Discussion

No community discussion yet for this question.