ISEB-PM1 · Question #605
ISEB-PM1 Question #605: Real Exam Question with Answer & Explanation
The correct answer is D. identification of project risks.. See the full explanation below for the reasoning.
Question
Risk mitigation includes all but which of the following:
Options
- Aperforming contingent planning
- BObtaining insurance against loss
- CDeveloping system (policies, procedures, responsibilities)
- Didentification of project risks.
- Edeveloping planning alternatives