nerdexam
BCS-ISEB

ISEB-PM1 · Question #605

ISEB-PM1 Question #605: Real Exam Question with Answer & Explanation

The correct answer is D. identification of project risks.. See the full explanation below for the reasoning.

Question

Risk mitigation includes all but which of the following:

Options

  • Aperforming contingent planning
  • BObtaining insurance against loss
  • CDeveloping system (policies, procedures, responsibilities)
  • Didentification of project risks.
  • Edeveloping planning alternatives