ISEB-PM1 · Question #405
Which document contains initial requirements that satisfy stakeholders' needs and expectations?
The correct answer is A. Project charter. A Project Charter formally authorizes a project and documents high-level requirements that satisfy stakeholder needs and expectations - it's the foundational document that captures what stakeholders want before detailed planning begins. Why the distractors are wrong: B. Project…
Question
Which document contains initial requirements that satisfy stakeholders' needs and expectations?
Options
- AProject charter
- BProject management plan
- CProject statement of work
- DProject scope statement
How the community answered
(42 responses)- A71% (30)
- B17% (7)
- C5% (2)
- D7% (3)
Explanation
A Project Charter formally authorizes a project and documents high-level requirements that satisfy stakeholder needs and expectations - it's the foundational document that captures what stakeholders want before detailed planning begins.
Why the distractors are wrong:
- B. Project management plan - created after the charter; it details how to execute, monitor, and control the project, not initial stakeholder requirements
- C. Project statement of work (SOW) - describes the products or services to be delivered, typically provided by the customer as an input to the charter, not an output that satisfies stakeholder needs
- D. Project scope statement - developed during planning to define detailed scope boundaries; it's too granular and comes too late in the process to be the initial requirements document
Memory tip: Think of the charter as the project's "birth certificate" - it's the first official document that legitimizes the project and captures what stakeholders need at a high level. If the question mentions initial, authorize, or stakeholder needs, think Charter.