ISEB-PM1 · Question #404

Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?

The correct answer is A. Monitor and Control Project Work. Monitor and Control Project Work (A) is correct because this process is specifically designed to track, review, and regulate the overall progress and performance of a project against the project management plan - it's the "watchdog" process that compares actual performance to…

Project Control

Question

Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?

Options

  • AMonitor and Control Project Work
  • BDirect and Manage Project Execution
  • CMonitor and Control Risk
  • DPerform Integrated Change Control

How the community answered

(50 responses)
  • A
    78% (39)
  • B
    6% (3)
  • C
    12% (6)
  • D
    4% (2)

Explanation

Monitor and Control Project Work (A) is correct because this process is specifically designed to track, review, and regulate the overall progress and performance of a project against the project management plan - it's the "watchdog" process that compares actual performance to planned performance across all knowledge areas.

Why the distractors are wrong:

  • B (Direct and Manage Project Execution) is about doing the work, not watching over it - it's execution, not oversight.
  • C (Monitor and Control Risk) is a narrower process focused only on risk responses and identifying new risks, not overall project performance.
  • D (Perform Integrated Change Control) handles reviewing and approving change requests, not monitoring performance against the plan.

Memory tip: Think of "Monitor and Control Project Work" as the project's dashboard - it gives you the big picture view of how the entire project is tracking. If you see words like reviewing, tracking, regulating, or performance objectives without a specific domain (risk, scope, cost), that's your signal to pick this process over the more specialized ones.

Topics

#monitor and control#performance objectives#project work#process definition