Reviewing, tracking, and regulating the process to meet performance objectives defined in the project management plan are part of which process?

Options

  • AMonitor and Control Project Work
  • BDirect and Manage Project Execution
  • CMonitor and Control Risk
  • DPerform Integrated Change Control