ISEB-PM1 · Question #406
The decision to approve or reject a particular change request is made in which of the following processes?
The correct answer is A. Perform Integrated Change Control. Perform Integrated Change Control is the process specifically designed to review, evaluate, and approve or reject change requests - it's the formal decision-making gate for all changes to the project baseline. Monitor and Control Project Work (B) tracks performance and…
Question
The decision to approve or reject a particular change request is made in which of the following processes?
Options
- APerform Integrated Change Control
- BMonitor and Control Project Work
- CDevelop Project Management Plan
- DDirect and Manage Project Execution
How the community answered
(28 responses)- A71% (20)
- B18% (5)
- C7% (2)
- D4% (1)
Explanation
Perform Integrated Change Control is the process specifically designed to review, evaluate, and approve or reject change requests - it's the formal decision-making gate for all changes to the project baseline. Monitor and Control Project Work (B) tracks performance and identifies variances but doesn't make change approval decisions. Develop Project Management Plan (C) creates the plan upfront and isn't an ongoing change-control mechanism. Direct and Manage Project Execution (D) implements approved changes but has no authority to approve or reject them.
Memory tip: Think of Integrated Change Control as the "change courtroom" - it's where every change request goes before a judge (the Change Control Board) to receive a verdict of approved or rejected. No change gets implemented without passing through this court first.