Who authorizes a project?
The correct answer is A. Sponsor. The Sponsor authorizes a project because they hold the organizational authority and funding to formally approve the project's existence, scope, and resources - this is a foundational concept in both PMI's PMBOK and PRINCE2 frameworks. B (Project Manager) is wrong: the PM is…
Question
Who authorizes a project?
Options
- ASponsor
- BProject manager
- CProject team
- DBuyer
How the community answered
(14 responses)- A71% (10)
- B7% (1)
- C7% (1)
- D14% (2)
Explanation
The Sponsor authorizes a project because they hold the organizational authority and funding to formally approve the project's existence, scope, and resources - this is a foundational concept in both PMI's PMBOK and PRINCE2 frameworks.
- B (Project Manager) is wrong: the PM is appointed by the sponsor to lead execution, not to authorize the project itself.
- C (Project Team) is wrong: the team carries out the work but has no authority to sanction or fund the project.
- D (Buyer) is wrong: a buyer may trigger a project through a contract, but authorization is an internal governance act performed by the sponsoring organization, not the customer.
Memory tip: Think of the sponsor as the project's parent - they give birth to it (authorization), fund it, and are ultimately accountable for its business case. The PM is the manager who runs the day-to-day once the project is alive.