A person is writing a document identifying the business need for a project and is including a description of the product created by the project. She includes a list of stakeholders and pre assigned…
The correct answer is C. The sponsor or the project manager. You've hit your session limit · resets 5:20pm (America/New_York)
The Project Management Lifecycle
Question
A person is writing a document identifying the business need for a project and is including a description of the product created by the project. She includes a list of stakeholders and pre assigned resources. What is the role of this person on the project?
Options
- AThe project manager for the project or a company functional manager
- BA member of the project management team working at the direction of the project manager
- CThe sponsor or the project manager
- DA manager or executive in the organization who is higher in the corporate hierarchy than the
How the community answered
(42 responses)- A17% (7)
- B5% (2)
- C74% (31)
- D5% (2)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)
Topics
#project charter#project sponsor#project initiation#stakeholders