A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:

The correct answer is B. Confirm that all the stakeholders have had input to the scope. You've hit your session limit · resets 5:20pm (America/New_York)

The Project Management Lifecycle

Question

A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:

Options

  • ACreate a project scope statement.
  • BConfirm that all the stakeholders have had input to the scope.
  • CAnalyze project risk.
  • DBegin work on a project management plan.

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    78% (32)
  • C
    5% (2)
  • D
    15% (6)

Explanation

You've hit your session limit · resets 5:20pm (America/New_York)

Topics

#project charter#stakeholder engagement#scope management#project initiation