Generally, when is the BEST time to create a procurement management plan?

The correct answer is B. Preceding the Conduct Procurement process. You've hit your session limit · resets 5:20pm (America/New_York)

Project Planning

Question

Generally, when is the BEST time to create a procurement management plan?

Options

  • AAfter the contract is signed
  • BPreceding the Conduct Procurement process
  • CDuring project initiating
  • DWhen updating the procurement management plan

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    85% (22)
  • C
    8% (2)
  • D
    4% (1)

Explanation