All the following are needed to create the WBS EXCEPT:
The correct answer is B. Quality measurements. You've hit your session limit · resets 5:20pm (America/New_York)
Project Planning
Question
All the following are needed to create the WBS EXCEPT:
Options
- AOrganizational process assets.
- BQuality measurements.
- CRequirements documentation.
- DProject scope statement.
How the community answered
(33 responses)- A9% (3)
- B82% (27)
- C3% (1)
- D6% (2)
Explanation
You've hit your session limit · resets 5:20pm (America/New_York)
Topics
#WBS#work breakdown structure#planning inputs