nerdexam
PMIPMI

CAPM · Question #534

CAPM Question #534: Real Exam Question with Answer & Explanation

The correct answer is C: Work package level. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work. What should the project manager answer?

Options

  • AActivity level
  • BDeliverable level
  • CWork package level
  • DTask level

Topics

#WBS#Decomposition#Work Package#Scope Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions