CAPM · Question #534
CAPM Question #534: Real Exam Question with Answer & Explanation
The correct answer is C: Work package level. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is developing the work breakdown structure (WBS) for a project. The team is asking at what level should they decompose their assigned work. What should the project manager answer?
Options
- AActivity level
- BDeliverable level
- CWork package level
- DTask level
Topics
#WBS#Decomposition#Work Package#Scope Management