CAPM · Question #416

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented it for decision. What was project manager trying to do?

The correct answer is C. Make sure management is aware of the change. The scenario describes the integrated change control process: the PM received the request, documented it (formal record), reviewed it with the team (analysis), and then presented it for decision. This sequence is the PM executing their responsibility to ensure that management…

Predictive, Plan-Based Methodologies

Question

A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented it for decision. What was project manager trying to do?

Options

  • ADevelop consensus among stakeholders
  • BGet the budget approved for change
  • CMake sure management is aware of the change
  • DGet approval from the change control board

How the community answered

(15 responses)
  • A
    7% (1)
  • B
    7% (1)
  • C
    87% (13)

Explanation

The scenario describes the integrated change control process: the PM received the request, documented it (formal record), reviewed it with the team (analysis), and then presented it for decision. This sequence is the PM executing their responsibility to ensure that management is informed and aware of the change before any decision is made. Option D (CCB approval) is tempting, but the question emphasizes awareness and process-the PM is surfacing the change upward. A and B are not supported by the actions described.

Topics

#Change Management#Communication#Decision Making