The correct answer is C: Make sure management is aware of the change. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A Project manager received a change request from a key stakeholder, documented it reviewed it with the team, and then presented it for decision. What was project manager trying to do?
Options
- ADevelop consensus among stakeholders
- BGet the budget approved for change
- CMake sure management is aware of the change
- DGet approval from the change control board
Topics
#Change Management#Communication#Decision Making