nerdexam
PMIPMI

CAPM · Question #415

CAPM Question #415: Real Exam Question with Answer & Explanation

The correct answer is C: Under budget, behind schedule. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

What CPI > 1 and SPI < 1 mean?

Options

  • AUnder budget ahead of schedule
  • BOver budget, behind schedule
  • CUnder budget, behind schedule
  • DOver budget, ahead of schedule

Topics

#Earned Value Management#CPI#SPI#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions