nerdexam
PMIPMI

CAPM · Question #414

CAPM Question #414: Real Exam Question with Answer & Explanation

The correct answer is A: Engage customer earlier. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

A project was sent for early customer testing and the customer reported that some of the features do not features do not meet the requirements. What should the project manager have done to avoid this scenario?

Options

  • AEngage customer earlier
  • BConduct quality audits
  • CValidate Scope
  • DValidate quality requirements

Topics

#Customer collaboration#Requirements management#Early feedback#Stakeholder engagement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions