CAPM · Question #417
What is the main purpose of Project Quality Management?
The correct answer is C. To fulfill project requirements of both quality and grade. According to the PMBOK Guide, Project Quality Management focuses on fulfilling the quality requirements and grade requirements established for the project-no more, no less. Option D (exceed expectations) describes gold plating, which is actually an anti-pattern in quality…
Question
Options
- ATo meet customer requirements by overworking the team
- BTo fulfill project schedule objectives by rushing planned inspections
- CTo fulfill project requirements of both quality and grade
- DTo exceed customer expectations
How the community answered
(17 responses)- B6% (1)
- C88% (15)
- D6% (1)
Explanation
According to the PMBOK Guide, Project Quality Management focuses on fulfilling the quality requirements and grade requirements established for the project-no more, no less. Option D (exceed expectations) describes gold plating, which is actually an anti-pattern in quality management. Option A (overworking the team) and B (rushing inspections) are poor practices. Quality management is about meeting defined requirements through planned and systematic processes.