PMIPMI
CAPM · Question #384
CAPM Question #384: Real Exam Question with Answer & Explanation
The correct answer is B: Acquire Resources. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What is the process of ensuring that project resources are assigned and available?
Options
- AControl Resources
- BAcquire Resources
- CControl Resources
- DPlan Procurement Management
Topics
#Acquire Resources#Resource Management#Project Execution