PMIPMI
CAPM · Question #385
CAPM Question #385: Real Exam Question with Answer & Explanation
The correct answer is B: 15 days. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
The project manager has following information about duration for an activity: * Most likely [tM] - 15 days * Pessimistic [tP] - 20 days * Optimistic [tO] - 10 days What is the estimated duration of this activity, according to the triangular distribution technique?
Options
- A10 days
- B15 days
- C12.5 days
- D5 days
Topics
#Activity duration estimation#Triangular distribution#Project schedule management
Community Discussion
No community discussion yet for this question.