nerdexam
PMIPMI

CAPM · Question #385

CAPM Question #385: Real Exam Question with Answer & Explanation

The correct answer is B: 15 days. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

The project manager has following information about duration for an activity: * Most likely [tM] - 15 days * Pessimistic [tP] - 20 days * Optimistic [tO] - 10 days What is the estimated duration of this activity, according to the triangular distribution technique?

Options

  • A10 days
  • B15 days
  • C12.5 days
  • D5 days

Topics

#Activity duration estimation#Triangular distribution#Project schedule management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions