nerdexam
PMI

CAPM · Question #385

The project manager has following information about duration for an activity: Most likely [tM] - 15 days Pessimistic [tP] - 20 days Optimistic [tO] - 10 days What is the estimated duration of this act

The correct answer is B. 15 days. Using the triangular distribution formula - a simple average of the three estimates - yields (10 + 15 + 20) / 3 = 15 days.

Predictive, Plan-Based Methodologies

Question

The project manager has following information about duration for an activity:
  • Most likely [tM] - 15 days
  • Pessimistic [tP] - 20 days
  • Optimistic [tO] - 10 days What is the estimated duration of this activity, according to the triangular distribution technique?

Options

  • A10 days
  • B15 days
  • C12.5 days
  • D5 days

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    77% (24)
  • C
    3% (1)
  • D
    13% (4)

Why each option

Using the triangular distribution formula - a simple average of the three estimates - yields (10 + 15 + 20) / 3 = 15 days.

A10 days

10 days is the optimistic estimate (tO) alone and is not the result of applying any three-point estimation formula combining all three input values.

B15 daysCorrect

The triangular distribution formula is (tO + tM + tP) / 3 = (10 + 15 + 20) / 3 = 45 / 3 = 15 days. Unlike the PERT beta distribution formula - (tO + 4tM + tP) / 6 - which weights the most likely estimate four times, the triangular distribution treats all three estimates equally as a simple arithmetic mean, producing 15 days in this case.

C12.5 days

12.5 days does not result from any standard three-point estimation formula - neither triangular nor PERT beta - applied to the given values of 10, 15, and 20.

D5 days

5 days represents the difference between the optimistic and most likely estimates and has no basis as a duration estimate under any recognized three-point distribution technique.

Concept tested: Triangular distribution three-point estimation calculation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Activity duration estimation#Triangular distribution#Project schedule management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice