nerdexam
PMIPMI

CAPM · Question #383

CAPM Question #383: Real Exam Question with Answer & Explanation

The correct answer is B: Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

The activity tailoring is necessary because:

Options

  • Athe members of the project team need to select the appropriate order of every tool, technique, input, and output listed in the PMBOK Guide, this is required for all projects.
  • BEach project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide
  • Cthe members of the project team need to understand the PMBOK Guide processes, which are applied to all projects
  • DEach project is unique, and the project team must plain how to apply all the tools, techniques, inputs, and outputs in the PMBOK Guide

Topics

#Tailoring#Project Uniqueness#PMBOK Guide Concepts

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions