CAPM · Question #377

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

The correct answer is D. Perform Integrated Change Control. Perform Integrated Change Control is the process where the project manager formally reviews change requests alongside deliverables and the project management plan to evaluate and disposition proposed changes.

Predictive, Plan-Based Methodologies

Question

A project manager is reviewing the change requests, deliverables, and the project plan in Which project management process does this review belong?

Options

  • AMonitor and Control Project Work
  • BDirect and Manage Project Work
  • CClose Project or Phase
  • DPerform Integrated Change Control

How the community answered

(17 responses)
  • B
    12% (2)
  • C
    6% (1)
  • D
    82% (14)

Why each option

Perform Integrated Change Control is the process where the project manager formally reviews change requests alongside deliverables and the project management plan to evaluate and disposition proposed changes.

AMonitor and Control Project Work

Monitor and Control Project Work tracks and reviews overall project progress against the plan but does not formally process or approve individual change requests.

BDirect and Manage Project Work

Direct and Manage Project Work focuses on executing the planned work and implementing approved changes - it does not evaluate or approve change requests.

CClose Project or Phase

Close Project or Phase finalizes all activities to formally complete the project or phase and does not involve reviewing or processing change requests.

DPerform Integrated Change ControlCorrect

Perform Integrated Change Control involves reviewing all change requests, approving changes, and managing changes to deliverables, project documents, and the project management plan. It is the specific process where change requests are formally evaluated in the context of the existing plan and deliverables to maintain project integrity and prevent scope creep.

Concept tested: Perform Integrated Change Control process inputs

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Integrated Change Control#Change Management#PMBOK Processes#Project Integration Management