CAPM · Question #378

Which organizational process asset can make an impact on the outcome of a project?

Sign in or unlock CAPM to reveal the answer and full explanation for question #378. The question stem and answer options stay visible for context.

Project Management Fundamentals and Core Concepts

Question

Which organizational process asset can make an impact on the outcome of a project?

Options

  • APolitical climate
  • BLeadership style
  • CFinancial data repository
  • DOrganizational structure types

Unlock CAPM to see the answer

You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Organizational Process Assets (OPA)#Enterprise Environmental Factors (EEF)#Project environment#Project resources