What is an output of the plan resource management process?
The correct answer is B. Risk register. The risk register is updated as a project documents output of the Plan Resource Management process when resource-related risks are identified during planning.
Question
Options
- AProject charter
- BRisk register
- CScope baseline
- DStakeholder register
How the community answered
(23 responses)- A4% (1)
- B96% (22)
Why each option
The risk register is updated as a project documents output of the Plan Resource Management process when resource-related risks are identified during planning.
The project charter is an output of the Develop Project Charter process in the Integration Management knowledge area and is not produced during Plan Resource Management.
During Plan Resource Management, the team identifies risks tied to resource availability, skill gaps, and team structure, which results in updates to the risk register as a project documents output per PMBOK 6. Among the choices provided, the risk register is the only option that appears as any form of output from this process.
The scope baseline is an output of the Create WBS process within the Scope Management knowledge area and has no connection to resource planning.
The stakeholder register is an output of the Identify Stakeholders process in Stakeholder Management and is not produced during Plan Resource Management.
Concept tested: Outputs of the Plan Resource Management process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok