What is an output of the plan resource management process?

The correct answer is B. Risk register. The risk register is updated as a project documents output of the Plan Resource Management process when resource-related risks are identified during planning.

Predictive, Plan-Based Methodologies

Question

What is an output of the plan resource management process?

Options

  • AProject charter
  • BRisk register
  • CScope baseline
  • DStakeholder register

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    96% (22)

Why each option

The risk register is updated as a project documents output of the Plan Resource Management process when resource-related risks are identified during planning.

AProject charter

The project charter is an output of the Develop Project Charter process in the Integration Management knowledge area and is not produced during Plan Resource Management.

BRisk registerCorrect

During Plan Resource Management, the team identifies risks tied to resource availability, skill gaps, and team structure, which results in updates to the risk register as a project documents output per PMBOK 6. Among the choices provided, the risk register is the only option that appears as any form of output from this process.

CScope baseline

The scope baseline is an output of the Create WBS process within the Scope Management knowledge area and has no connection to resource planning.

DStakeholder register

The stakeholder register is an output of the Identify Stakeholders process in Stakeholder Management and is not produced during Plan Resource Management.

Concept tested: Outputs of the Plan Resource Management process

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Resource Management#Process Outputs#Planning Processes#PMBOK Guide

Community Discussion

No community discussion yet for this question.

Full CAPM Practice