CAPM · Question #344
CAPM Question #344: Real Exam Question with Answer & Explanation
The correct answer is C: Represents how and when the project will deliver the results defined in the project scope.. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
What is the purpose of the project schedule management?
Options
- AEstimates specific time and the deadline when the products, services and results will be delivered.
- BDetermines in details the resources and time that each task will require to be done
- CRepresents how and when the project will deliver the results defined in the project scope.
- DIt provides the relationships among the project activities and their risks.
Topics
#Project Schedule Management#Project Planning#Project Delivery#Knowledge Area Purpose