CAPM · Question #346
CAPM Question #346: Real Exam Question with Answer & Explanation
The correct answer is D: Lessons learned repository. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
What document gathers all of the lessons learned at the end of a phase or project?
Options
- ALessons learned register
- BLessons learned list
- CLessons learned project asset
- DLessons learned repository
Topics
#Lessons Learned#Organizational Process Assets#Project Closure#Knowledge Management