nerdexam
PMI

CAPM · Question #346

What document gathers all of the lessons learned at the end of a phase or project?

The correct answer is D. Lessons learned repository. The Lessons Learned Repository is an organizational process asset (OPA) that serves as the final storage location where all lessons learned are gathered and preserved at the end of a project phase or project. Throughout the project, the Lessons Learned Register (a project documen

Predictive, Plan-Based Methodologies

Question

What document gathers all of the lessons learned at the end of a phase or project?

Options

  • ALessons learned register
  • BLessons learned list
  • CLessons learned project asset
  • DLessons learned repository

How the community answered

(22 responses)
  • B
    5% (1)
  • C
    5% (1)
  • D
    91% (20)

Explanation

The Lessons Learned Repository is an organizational process asset (OPA) that serves as the final storage location where all lessons learned are gathered and preserved at the end of a project phase or project. Throughout the project, the Lessons Learned Register (a project document) is maintained to capture ongoing knowledge. At project closure, those entries are compiled and transferred into the repository, making it available to future projects. The other options - 'lessons learned list,' 'lessons learned project asset,' and 'lessons learned register' - are either informal terms or refer to the living project document used during execution, not the end-of-project storage artifact.

Topics

#Lessons Learned#Organizational Process Assets#Project Closure#Knowledge Management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice