PMIPMI
CAPM · Question #330
CAPM Question #330: Real Exam Question with Answer & Explanation
The correct answer is C: Initiate project closure.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?
Options
- AInitiate change control.
- BAddress risk mitigation.
- CInitiate project closure.
- DEscalate this to the project sponsor.
Topics
#Project Closure#Project Termination#Business Value#Risk Management
Community Discussion
No community discussion yet for this question.