nerdexam
PMIPMI

CAPM · Question #330

CAPM Question #330: Real Exam Question with Answer & Explanation

The correct answer is C: Initiate project closure.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project is in its final stages when a competitor releases a similar product. This could make the project redundant. What should the project manager do next?

Options

  • AInitiate change control.
  • BAddress risk mitigation.
  • CInitiate project closure.
  • DEscalate this to the project sponsor.

Topics

#Project Closure#Project Termination#Business Value#Risk Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions