nerdexam
PMIPMI

CAPM · Question #331

CAPM Question #331: Real Exam Question with Answer & Explanation

The correct answer is A: Sprint backlog. See the full explanation below for the reasoning.

Agile Frameworks/Methodologies

Question

An executive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning. Which two of the following items should be included in the planning? (Choose two.)

Options

  • ASprint backlog
  • BIncrements
  • CDaily scrum
  • DSprint retrospective
  • ESprint review

Topics

#Agile Artifacts#Scrum Artifacts#Sprint Backlog#Increment

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions