An executive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project mana

The correct answer is A. Sprint backlog B. Increments. In Scrum, there are three official artifacts: the Product Backlog, the Sprint Backlog, and the Increment. Since the team already identified project events, the missing items must be artifacts. Of the answer choices, Sprint Backlog (A) and Increments (B) are Scrum artifacts. Daily

Agile Frameworks/Methodologies

Question

An executive team is performing the kickoff meeting and planning the project management approach. After defining project events, one team member argues that the artifacts are missing. The project manager coaches the team to complete the planning. Which two of the following items should be included in the planning? (Choose two.)

Options

  • ASprint backlog
  • BIncrements
  • CDaily scrum
  • DSprint retrospective
  • ESprint review

How the community answered

(28 responses)
  • A
    86% (24)
  • C
    7% (2)
  • D
    4% (1)
  • E
    4% (1)

Explanation

In Scrum, there are three official artifacts: the Product Backlog, the Sprint Backlog, and the Increment. Since the team already identified project events, the missing items must be artifacts. Of the answer choices, Sprint Backlog (A) and Increments (B) are Scrum artifacts. Daily Scrum (C), Sprint Retrospective (D), and Sprint Review (E) are Scrum events/ceremonies - they would already be covered in the events discussion. This question tests the distinction between Scrum artifacts (what is produced) and Scrum events (scheduled activities/meetings).

Topics

#Agile Artifacts#Scrum Artifacts#Sprint Backlog#Increment