nerdexam
PMIPMI

CAPM · Question #332

CAPM Question #332: Real Exam Question with Answer & Explanation

The correct answer is A: Follow the risk response plan and allocate resources, if needed, to overcome the issue.. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months. What should the project manager do to overcome this problem and put the project back on track?

Options

  • AFollow the risk response plan and allocate resources, if needed, to overcome the issue.
  • BAccept any penalties that might occur and continue working as initially planned.
  • CConsult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.
  • DExtend the time of product delivery and use management reserve to cover any losses.

Topics

#Risk Management#Issue Resolution#Contingency Planning#Project Recovery

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions