nerdexam
PMI

CAPM · Question #332

Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months. What should the project manager do to overcome this problem and

The correct answer is A. Follow the risk response plan and allocate resources, if needed, to overcome the issue.. When a risk event (supplier failure) has materialized, the correct first response is to execute the pre-established risk response plan. The risk response plan should already include contingency actions for supplier-related risks, such as finding alternative suppliers or reallocat

Predictive, Plan-Based Methodologies

Question

Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months. What should the project manager do to overcome this problem and put the project back on track?

Exhibit

CAPM question #332 exhibit

Options

  • AFollow the risk response plan and allocate resources, if needed, to overcome the issue.
  • BAccept any penalties that might occur and continue working as initially planned.
  • CConsult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.
  • DExtend the time of product delivery and use management reserve to cover any losses.

How the community answered

(54 responses)
  • A
    72% (39)
  • B
    15% (8)
  • C
    7% (4)
  • D
    6% (3)

Explanation

When a risk event (supplier failure) has materialized, the correct first response is to execute the pre-established risk response plan. The risk response plan should already include contingency actions for supplier-related risks, such as finding alternative suppliers or reallocating resources. Following this plan (A) is proactive and structured. Accepting penalties (B) is passive and does not recover the schedule. Consulting legal (C) may be a secondary action but is not how the schedule gets back on track. Extending delivery (D) and using management reserve addresses cost but does not solve the underlying schedule problem.

Topics

#Risk Management#Issue Resolution#Contingency Planning#Project Recovery

Community Discussion

No community discussion yet for this question.

Full CAPM Practice