PMIPMI
CAPM · Question #332
CAPM Question #332: Real Exam Question with Answer & Explanation
The correct answer is A: Follow the risk response plan and allocate resources, if needed, to overcome the issue.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Construction of a building has stopped due to a supplier's failure to deliver concrete. The project schedule is behind by three months. What should the project manager do to overcome this problem and put the project back on track?
Options
- AFollow the risk response plan and allocate resources, if needed, to overcome the issue.
- BAccept any penalties that might occur and continue working as initially planned.
- CConsult the legal department and subject matter experts (SMEs) regarding what to do to avoid failure.
- DExtend the time of product delivery and use management reserve to cover any losses.
Topics
#Risk Management#Issue Resolution#Contingency Planning#Project Recovery
Community Discussion
No community discussion yet for this question.