How does a requirements traceability matrix help to determine whether a product is ready for delivery?
Options
- AIt confirms the completion of all stories in the backlog.
- BIt tracks links between the approved requirements and each work product.
- CIt assesses the quality of test cases and expected results.
- DIt captures assigned tasks and their estimated durations.