CAPM · Question #328

CAPM Question #328: Real Exam Question with Answer & Explanation

The correct answer is A: Deliver the product.. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

All testing on a project has been performed successfully and all acceptance criteria have been met. What is the next step?

Options

  • ADeliver the product.
  • BSet up a go/no-go meeting.
  • CSet up a meeting with the sponsor.
  • DWait for the next sprint.

Topics

#Project Closure#Deliverables#Acceptance Criteria#Product Delivery