PMIPMI
CAPM · Question #327
CAPM Question #327: Real Exam Question with Answer & Explanation
The correct answer is C: Consult the communications management plan.. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A team member, who is close to an influential stakeholder, has joined the project team. The stakeholder is routing requests for multiple reports through the new team member, and the team member reaches out to the project manager regarding this. What should the project manager do first?
Options
- AUpdate the communications management plan.
- BManage stakeholder engagement.
- CConsult the communications management plan.
- DForward the status reports to the stakeholder.
Topics
#Communications Management#Stakeholder Engagement#Communications Management Plan#Project Processes
Community Discussion