PMIPMI
CAPM · Question #312
CAPM Question #312: Real Exam Question with Answer & Explanation
The correct answer is B: -12. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
Options
- A1.15
- B-12
- C12
- D38
Topics
#Earned Value Management (EVM)#Schedule Variance (SV)#Project Performance Measurement#Predictive Project Management
Community Discussion
No community discussion yet for this question.