CAPM · Question #312
A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?
The correct answer is B. -12. Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV). In this scenario, the Planned Value (work that should have been completed) is 25 days, and the Earned Value (work actually accomplished) is 13 days. Therefore: SV = 13 – 25 = –12. A negative SV means the project is
Question
Options
- A1.15
- B-12
- C12
- D38
How the community answered
(45 responses)- A11% (5)
- B78% (35)
- C2% (1)
- D9% (4)
Explanation
Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV). In this scenario, the Planned Value (work that should have been completed) is 25 days, and the Earned Value (work actually accomplished) is 13 days. Therefore: SV = 13 – 25 = –12. A negative SV means the project is behind schedule. The value 1.15 resembles a Schedule Performance Index (SPI), 12 would indicate a positive variance (ahead of schedule), and 38 is the sum rather than the difference - none of which correctly apply here.
Topics
Community Discussion
No community discussion yet for this question.