nerdexam
PMIPMI

CAPM · Question #312

CAPM Question #312: Real Exam Question with Answer & Explanation

The correct answer is B: -12. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

A project manager is reporting the project performance as 25 days worth of work completed against 13 days originally planned. What is the schedule variance (SV)?

Options

  • A1.15
  • B-12
  • C12
  • D38

Topics

#Earned Value Management (EVM)#Schedule Variance (SV)#Project Performance Measurement#Predictive Project Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions