A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and produc

The correct answer is D. Inspection. Inspection is the process of formally examining a work product, deliverable, or result to determine conformance to documented requirements and acceptance criteria. It involves measurement, review, and structured evaluation - exactly what the sponsor is doing here. Brainstorming i

Predictive, Plan-Based Methodologies

Question

A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?

Options

  • ABrainstorming
  • BPrototyping
  • CDecision making
  • DInspection

How the community answered

(62 responses)
  • A
    2% (1)
  • B
    5% (3)
  • C
    6% (4)
  • D
    87% (54)

Explanation

Inspection is the process of formally examining a work product, deliverable, or result to determine conformance to documented requirements and acceptance criteria. It involves measurement, review, and structured evaluation - exactly what the sponsor is doing here. Brainstorming is an idea-generation technique, prototyping is an iterative modeling method, and decision making is a process for selecting among options. None of those describe the formal examination of a finished deliverable against its acceptance criteria.

Topics

#Inspection#Quality Control#Deliverable verification#Acceptance criteria