CAPM · Question #311
A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and produc
The correct answer is D. Inspection. Inspection is the process of formally examining a work product, deliverable, or result to determine conformance to documented requirements and acceptance criteria. It involves measurement, review, and structured evaluation - exactly what the sponsor is doing here. Brainstorming i
Question
Options
- ABrainstorming
- BPrototyping
- CDecision making
- DInspection
How the community answered
(62 responses)- A2% (1)
- B5% (3)
- C6% (4)
- D87% (54)
Explanation
Inspection is the process of formally examining a work product, deliverable, or result to determine conformance to documented requirements and acceptance criteria. It involves measurement, review, and structured evaluation - exactly what the sponsor is doing here. Brainstorming is an idea-generation technique, prototyping is an iterative modeling method, and decision making is a process for selecting among options. None of those describe the formal examination of a finished deliverable against its acceptance criteria.
Topics
Community Discussion
No community discussion yet for this question.