A project manager has joined the sponsor to verify the last deliverable of the project. The sponsor is measuring and examining the deliverable to determine whether it meets the requirements and product acceptance criteria. Which activity is being performed?
Options
- ABrainstorming
- BPrototyping
- CDecision making
- DInspection