CAPM · Question #310
Which of the following is part of the project sponsor's responsibility?
The correct answer is D. Advocating the business value. The project sponsor's primary role is to champion the project at the executive or organizational level - which means advocating for its business value, securing resources, and removing organizational obstacles. Tracking, auditing, and monitoring are operational and control…
Question
Options
- ATracking the business value
- BAuditing the business value
- CMonitoring the business value
- DAdvocating the business value
How the community answered
(62 responses)- A5% (3)
- B2% (1)
- C3% (2)
- D90% (56)
Explanation
The project sponsor's primary role is to champion the project at the executive or organizational level - which means advocating for its business value, securing resources, and removing organizational obstacles. Tracking, auditing, and monitoring are operational and control activities typically owned by the project manager, PMO, or quality assurance functions. The sponsor ensures the project remains strategically aligned and that its value proposition is defended and promoted to senior stakeholders.
Topics
Community Discussion
No community discussion yet for this question.