nerdexam
PMIPMI

CAPM · Question #309

CAPM Question #309: Real Exam Question with Answer & Explanation

The correct answer is A: If the transition process was agreed upon during the build. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

The handoff of the first version of a software application to the operational team has taken a month longer than anticipated. How could this extended transition time have been avoided?

Options

  • AIf the transition process was agreed upon during the build
  • BIf the end-user documentation was more thorough
  • CIf the operation team members were trained externally
  • DIf the operations manager was invited to all sprint reviews

Topics

#Transition Planning#Handoff Management#Stakeholder Collaboration#Process Definition

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions