CAPM · Question #261
What is the primary benefit of the Manage Quality process?
The correct answer is A. Increases the probability of meeting quality objectives. The primary benefit of the Manage Quality process (formerly Quality Assurance in earlier PMBOK editions) is that it increases the probability of meeting the project's quality objectives by ensuring that quality policies, processes, and standards are being properly applied…
Question
Options
- AIncreases the probability of meeting quality objectives
- BEnhances the performance of the product being created
- CDefines quality roles and responsibilities
- DEnsures that the project is completed as originally planned
How the community answered
(33 responses)- A88% (29)
- B6% (2)
- C3% (1)
- D3% (1)
Explanation
The primary benefit of the Manage Quality process (formerly Quality Assurance in earlier PMBOK editions) is that it increases the probability of meeting the project's quality objectives by ensuring that quality policies, processes, and standards are being properly applied throughout the project. It is proactive - focused on process compliance and continuous improvement. Option B (enhancing the product) is more aligned with the Control Quality process, which inspects outputs. Option C (defining roles) occurs in the Plan Quality Management process. Option D (completing as planned) is too broad and not specific to quality management.