nerdexam
PMIPMI

CAPM · Question #262

CAPM Question #262: Real Exam Question with Answer & Explanation

The correct answer is C: An iterative scheduling and on-demand, pull-based scheduling will be required.. See the full explanation below for the reasoning.

Adaptive Frameworks/Methodologies

Question

Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?

Options

  • ADefining sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
  • BThe detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
  • CAn iterative scheduling and on-demand, pull-based scheduling will be required.
  • DTo address the full delivery schedule, a range of techniques may be needed and then need to be adapted.

Topics

#Adaptive scheduling#Iterative scheduling#Pull-based scheduling#Agile environments

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions