CAPM · Question #262
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
The correct answer is C. An iterative scheduling and on-demand, pull-based scheduling will be required.. In adaptive (Agile) environments, scheduling uses two primary techniques: iterative scheduling (work is planned and executed in fixed-length cycles called sprints or iterations) and on-demand, pull-based scheduling (team members pull work from a backlog as capacity allows, as in
Question
Options
- ADefining sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
- BThe detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
- CAn iterative scheduling and on-demand, pull-based scheduling will be required.
- DTo address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C91% (20)
Explanation
In adaptive (Agile) environments, scheduling uses two primary techniques: iterative scheduling (work is planned and executed in fixed-length cycles called sprints or iterations) and on-demand, pull-based scheduling (team members pull work from a backlog as capacity allows, as in Kanban). These approaches replace the rigid, fully-defined upfront schedule used in predictive environments. Option A describes a characteristic of predictive environments where planning steps are tightly coupled. Option B (keeping the schedule flexible) is partially true but too vague. Option D describes a hybrid or multi-methodology environment rather than a purely adaptive one.
Topics
Community Discussion
No community discussion yet for this question.