PMIPMI
CAPM · Question #262
CAPM Question #262: Real Exam Question with Answer & Explanation
The correct answer is C: An iterative scheduling and on-demand, pull-based scheduling will be required.. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
Which of the following conditions should the project manager consider when working on the scheduling for an adaptive environment?
Options
- ADefining sequencing, estimating activity durations, and developing a schedule model are so tightly linked that they are viewed as a single process.
- BThe detailed project schedule should remain flexible throughout the project to accommodate newly gained knowledge.
- CAn iterative scheduling and on-demand, pull-based scheduling will be required.
- DTo address the full delivery schedule, a range of techniques may be needed and then need to be adapted.
Topics
#Adaptive scheduling#Iterative scheduling#Pull-based scheduling#Agile environments
Community Discussion
No community discussion yet for this question.