CAPM · Question #260

CAPM Question #260: Real Exam Question with Answer & Explanation

The correct answer is A: Managing a project schedule. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which is an example of a technical project management skill?

Options

  • AManaging a project schedule
  • BDeveloping a project delivery strategy
  • CEstablishing a project team
  • DUnderstanding organizational objectives

Topics

#Technical Project Management Skills#Project Management Skills#Schedule Management