PMIPMI
CAPM · Question #253
CAPM Question #253: Real Exam Question with Answer & Explanation
The correct answer is D: Parametric estimation, three-point estimation, meetings. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
Options
- ABrainstorming, Monte Carlo simulation, analogous estimation
- BThree-point estimation, resources leveling, iterative burndown chart
- CMilestone charts, parametric estimation, schedule baseline
- DParametric estimation, three-point estimation, meetings
Topics
#Activity Duration Estimation#Schedule Management#Estimation Techniques#Predictive Planning
Community Discussion
No community discussion yet for this question.