CAPM · Question #253
Which set of tools and techniques is useful for estimating activity durations for the project schedule?
The correct answer is D. Parametric estimation, three-point estimation, meetings. Estimating activity durations uses techniques such as parametric estimation (using historical data and statistical relationships), three-point estimation (using optimistic, most likely, and pessimistic estimates - PERT), and meetings (to gather expert input). Option A is…
Question
Options
- ABrainstorming, Monte Carlo simulation, analogous estimation
- BThree-point estimation, resources leveling, iterative burndown chart
- CMilestone charts, parametric estimation, schedule baseline
- DParametric estimation, three-point estimation, meetings
How the community answered
(32 responses)- A3% (1)
- B3% (1)
- C6% (2)
- D88% (28)
Explanation
Estimating activity durations uses techniques such as parametric estimation (using historical data and statistical relationships), three-point estimation (using optimistic, most likely, and pessimistic estimates - PERT), and meetings (to gather expert input). Option A is incorrect because Monte Carlo simulation is a risk analysis tool, not a primary duration estimation technique. Option B includes resource leveling, which is a schedule optimization technique, not estimation. Option C includes milestone charts and schedule baseline, which are outputs/monitoring tools, not estimation techniques.
Topics
Community Discussion
No community discussion yet for this question.