nerdexam
PMIPMI

CAPM · Question #253

CAPM Question #253: Real Exam Question with Answer & Explanation

The correct answer is D: Parametric estimation, three-point estimation, meetings. See the full explanation below for the reasoning.

Predictive, Plan-Based Methodologies

Question

Which set of tools and techniques is useful for estimating activity durations for the project schedule?

Options

  • ABrainstorming, Monte Carlo simulation, analogous estimation
  • BThree-point estimation, resources leveling, iterative burndown chart
  • CMilestone charts, parametric estimation, schedule baseline
  • DParametric estimation, three-point estimation, meetings

Topics

#Activity Duration Estimation#Schedule Management#Estimation Techniques#Predictive Planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions